PSP Elsewedy, Egypt
PSP Elsewedy, Egypt
Branch in charge: Bremen, Germany
Destination: Cairo, Egypt
Cargo: Power Plant Equipment | Energy Project
Volume: 700 t
Job description:
Hansa Meyer Global has been nominated to fly 700 t of power plant equipment from FCA Hamburg, Germany and Leipzig, Germany to CFR Cairo Airport, Egypt.
The cargo originated from various European countries, e.g. Germany, the Czech Republic and Poland.
Initially the cargo was planned as sea freight shipment. The EPC Contractor decided on short notice to change to air freight transport due to the urgency resulting from the Egyptian president to set up new power plants in the country within a short period of time.