Our Case Studies in Philippines
Visayas Mindanao± 350kv DC interconnection EPC project, Philippines
Visayas Mindanao± 350kv DC interconnection EPC project, Philippines
Branch in charge: China
Destination: Cebu, Philippine/Mindanao, Philippine
Cargo:
Transformers and accessories
including 7 units Siemens transformers each 8.90x3.70x4.70(m) / 110.5tons & 4 Siemens transformers each 10.00x3.80x4.00(m) / 91.0 tons
Volume: 4023 frt
Job description:
Hansa Meyer Global Transport Shanghai was awarded to deliver all the shipments from China / Germany Siemens factory to the jobsite in Cebu Island / Mindanao Island in Philippine for 11 units transformers and accessories with DDU item up to site including manually setting on foundation.
Total Project duration only 8 months, moreover we faced the outbreaking of COVID-19 both in Germany and Philippine , and lots of limits by local government for measures of control COVID-19, we and project owner worked together and finally completed the delivery of all the transformers and accessories successfully.
The total project has a volume of approx.. 4023 FRT and includes heavy lifts 7@ 110.5 tons+4@ 91 tons
Turbine Generator
Turbine Generator
Branch in charge: Philippines
Destination: Petron Limay Bataan, Philippines
Cargo: Turbine Generator
Volume: 49,900.05 frt
Job description:
Direct shipment of a 72 t turbine generator from M.V. Wakasa by means of a multi-axle trailer.
Coal Fired Power Plant
Coal Fired Power Plant
Branch in charge: Philippines
Destination: Toledo, Cebu
Cargo: Coal Fired Power Plant, 82 MW
Volume: 38,385 frt
Job description:
Shipside receipt and transportation of a 170 t turbine generator and its accessories to Toledo Power Corp., total volume – 1,045 m3.
Ball Mill
Ball Mill
Branch in charge: Philippines
Destination: Masbate, Philippines
Cargo: Mill shell, Head and Accessories
Volume: 911 frt
Job description:
- Pick up from the place of origin (Melbourne and New Castle, Australia)
- Unloading/ receiving / customs clearance at Batangas port, Batangas City
- Roll on barge in Batangas port
- Delivery to PGPRC private port in Masbate
- Inland transportation to the mine site.
Telecom Equipment
Telecom Equipment
Branch in charge: Philippines
Destination: Visayas and Mindanao sites, Philippines
Cargo: Telecom equipment
Volume: 280 frt
Job description:
- Customs clearance and delivery to HMGT’s warehouse
- Warehousing and inventory
- Delivery to various sites in Visayas and Mindanao, Philippines
- Manual hauling of the equipment from the staging area up to the site
(Note: 80% of the sites are not passable by any type of vehicles, thus, manual hauling is required).
Substation Equipment
Substation Equipment
Branch in charge: Philippines
Destination: Binga / Itogon / Beguet, Philippines
Cargo: Transformers, Accessories and other Substation Equipment
Volume: 293.2 frt
Job description:
- FOB Shanghai, China to DDU Binga, Itogon, Benguet
- Customs clearance / DOF exemption
- Inland transport including unloading and spotting of transformer